City of Carmel
Project: 16-ENG-05
96th Street and Keystone Parkway Road Improvements
The 96th Street and Keystone Parkway Road Improvements project was awarded to Rieth-Riley Construction Co., Inc. by the City of Carmel in 2017. This project was a complete interchange reconstruction, under multiple phases, constructing a new bridge that elevated Keystone Parkway over 96th Street to improve traffic flow for the motoring public. Rieth-Riley performed the construction of a new two span bridge, MSE retaining walls, asphalt paving, concrete sidewalks, and concrete curb.
Asphalt- 68,000 Tons
MSE Wall- 68,000 SFT
Moment Slabs- 7,800 SYS
General Contractor: Rieth-Riley Construction
Owner: ITR Concession Company LLC.