Project Name: Oscoda Wurtsmith Airport Runway Improvement Project
Scope of work: Reconstruction of new blast pads and HMA cold milling and re-paving. The cold milling and paving was completed using 3-D technology.
Time-frame: 107 Calendar Days
Phasing: The project was completed in 4 phases to minimize the runway closure to 22 days.
National Asphalt Paving Association Quailty in Construction Award
Contractor: Rieth-Riley Construction