Coca Cola In Caledonia MI

Caledonia Michigan recently welcomed a new Lo Calorie facility. However, during construction directional signage, asphalt paving, and pavement markings were both needed to help produce a finished project. Rieth-Riley was chosen as the subcontractor for the job and begin working on the project in 2020 with the goal to finish the project by 2021. Materials used for the job include:

  • Asphalt Leveling Course 5,904 Tons
  • Asphalt Wearing Course 5,565 Tons
  • Total: 11,469 Tons

The project was completed on time without any issues.

Related Projects

Project Rapids

Paving project for large new warehouse project in Gaines Township, MI.  Rieth-Riley was hired to fine grade, pave, stripe and site signage.  Multiple pavement cross

Read More »
36th Street Marketplace

36th Street Marketplace

Another successful project completed by Rieth-Riley’s Grand Rapids team! The 36th Street Marketplace is now ready to host farmers’ and artisan markets, live music performances,

Read More »

Menards Parking Lot

Menards Parking Lot  For this project Rieth-Riley poured 4,000 LFT of curb and gutter.  Rieth-Riley also supplied 5,000 tons of #53 crushed concrete that was

Read More »

Request a Quote

Scroll to Top