Coca Cola In Caledonia MI

Caledonia Michigan recently welcomed a new Lo Calorie facility. However, during construction directional signage, asphalt paving, and pavement markings were both needed to help produce a finished project. Rieth-Riley was chosen as the subcontractor for the job and begin working on the project in 2020 with the goal to finish the project by 2021. Materials used for the job include:

  • Asphalt Leveling Course 5,904 Tons
  • Asphalt Wearing Course 5,565 Tons
  • Total: 11,469 Tons

The project was completed on time without any issues.